Full home rewire
Private residence — Pretoria East
Complete rewire of a 4-bedroom home including DB board upgrade, surge protection and Certificate of Compliance issued on completion.
- Challenge
- The 30-year-old wiring failed insulation testing and the DB board tripped intermittently, putting the family and appliances at risk.
- Solution
- We planned a 7-day rewire in phases so the family could stay on site, chased new conduit, installed a labelled Schneider DB and added whole-home surge protection.
- Outcome
- Every circuit passed insulation and continuity testing, a valid COC was issued the same week, and the client's insurer confirmed cover on the upgraded installation.